© Copyright MPA - M Payano 2014 -2020  Some projects throughout career of MPA members, include, but not limited to: -600 MW PC (Pulverized Coal) Plant – Optimization Study and EPC. -Chiller Plant Upgrade, NYC A. E. University. 3,500 Tons of Refrigeration. (Steam absorption units). -400 & 500 MW Gas Turbine Peaking Plant-EPC (Achieve savings of 23 Million dollars using equipment engineering and procurement value engineering strategies) -1600 MW Nuclear Power Plant-EPC –Not Yet Built (Estimated procurement budget of APPROX. $6.4 Billion.) -500 MW Refused Derived Fuel Plant-EPC -550 MW Natural Gas fired Combined Cycle Plant-EPC  East River Re-powering project with Con Edison 2 X 160 MW GTG & HRSG– 2003-2005 Waste to Energy Plant  300 MW– for Waste Management Easton, PA  2001-2002 Construction Management, Design-Engineering (retrofit). ASTORIA Generating Plant 5 with Con Edison – 1989-990 Replacement of Generation tube bank as well as superheater and reheaters on 380 MW Balanced draft unit.   RAVENSWOOD 1 (400 MW) – with Con Edison 1989-90  Replacement of Regular Condenser with All Titanium Condenser and associated Cooling water circuit. RAVENSWOOD 3 (1000 MW) – Operation, major maintenance 1988-89 of Combustion Engineering and Allis Chalmers cross compound Steam turbine generator and Balance of plant. INTERNATIONAL PROJECTS ITABO 1- Consultor for IMESGEG- Haina, Dom. Rep. 2003  IPP 125 MW – EPC – Retrofit of Coal Fuels systems, including replacement of all coal pulverizers (8), silos, controls, FGDs, El. Precipitators, waste ash pumps as well as some structural and electrical upgrades. SMITH ENRON-1994-1996 EPC-Combined Cycle185 MW, General Electric frame 7EA, HRSG (Heat Recovery Steam Generator), GE Steam Turbine - Puerto Plata, Dominican Republic. Work Scope:  Green field project build a new Gas turbine plant exhausting to heat recovery steam generators with supplemental firing to produce electric power (both gas turbine 80 MW and steam turbine 120 MW). Haina IV Steam Drum and Generating Bank Replacement 1995- 90 MW EPC-Replacement of Damaged (Cracked) Steam Drum after exhaustive metallurgical investigation to find root caused (Low cycle fatigue). To Replace Steam Drum with new enhanced metallurgical properties and all associated Generating tube banks and welds. Consultor through de Burns & Roe Enterprises -Cogentrix-San Pedro de Macorís, Dom. Rep. 2000-2001  EPC for HRSG with supplemental Fuel oil firing and all steam Circuits for 300 MW CC Plant. Tecnologias Unicas, C x A 138KV Electrical Transmission Line 1993- 1994- EPC of 138 KV Electrical transmission line between Santo Domingo and Santiago in Dominican Republic. AMONG OTHERS....